Pacific Highway Upgrade

Kempsey Bypass Construction

What has happened in April 2012

Macleay River and floodplain bridge

  • Continuation of Super T girder deliveries from Macksville to both Austral Eden and    Frederickton.
  • Completion of driven piling on the floodplain
  • Continuation of pier and headstock construction and girder erection for the floodplain section of the bridge.
  • Continuation of concrete deck pours for the floodplain section of the bridge.
  • Commencement of transfer of the northern rock platform to the southern side of the Macleay River.
  • Continuation of pile cap, pier and headstock construction on the Macleay River section of the bridge.
  • Girder erection on the river section of the bridge.

South Kempsey to Pola Creek

  • Continuation of construction of the bridges over the North Coast Railway Line, Boat Harbour Creek and South Kempsey interchange.
  • Continuation of bulk earthworks at the South Kempsey interchange.
  • Commencement of tie-in works near the Kempsey Indoor Sports Centre.
  • Continuation of Lyall Lane road works.
  • Completion of property access roads onto Crescent Head Road.

Pola Creek to Macleay River

  • Continuation of construction of the Pola Creek, Old Station Road and Inches Road bridges.
  • Continuation of flood mitigation works in the form of house raising across the floodplain.
  • Continuation of concrete paving and associated works.
  • Construction of approaches to Inches Road and Old Station Road overbridges.

Frederickton interchange

  • Continuation of placement of select pavement material, subsoils and drainage on Smithtown link.
  • Placement of pavement material on the Smithtown link.
  • Completion of concrete paving of the eastern roundabout.
  • Continuation of tie-in works at Smithtown link.

Key construction activities during May and June 2012

Macleay River and floodplain bridge

  • Continuation of Super T girder deliveries from Macksville to both Austral Eden and Frederickton.
  • Continuation of Super T girder erection on the river and floodplain.
  • Continuation of the delivery and erection of the precast concrete barriers.
  • Completion of the rock platform transfer from the north side to the south side of the Macleay River.
  • Start of bored piling from the southern rock platform.
  • Completion of pier and headstock construction for the floodplain section of the bridge.
  • Continuation of deck pours for the floodplain section of the bridge, moving north.
  • Continuation of pile cap, pier and headstock construction on the Macleay River section of the bridge.

South Kempsey to Pola Creek

  • Completion of construction of the Bingis Lane fauna underpass.
  • Completion of pavement sealing between Lyall Lane and Pola Creek.
  • Completion of property access roads onto Crescent Head Road.
  • Continuation of construction of the bridges over the North Coast Railway Line, Boat Harbour Creek and South Kempsey interchange.
  • Continuation of drainage from the southern interchange to North Coast Railway.
  • Continuation of construction of northbound ramp near the Kempsey Indoor Sports Centre.
  • Completion of drainage and bulk earthworks at the South Kempsey interchange.
  • Commencement of concrete pavement works between Crescent Head Road and Pola Creek.

Pola Creek to Macleay River

  • Completion of flood mitigation works in the form of house raising across the floodplain.
  • Completion of installation of drainage between Pola Creek and Old Station Road.
  • Continuation of construction of the Pola Creek bridge and approaches to Old Station Road and Inches Road bridges.
  • Continuation of concrete pavement and the commencement of concrete shoulder paving works.

Frederickton interchange

  • Continuation of placement of select pavement material, subsoils and drainage on the northbound off ramp to Smithtown. 
  • Start of tie-in works at Frederickton and northbound off ramp to Smithtown.
  • Start of asphalt works.
  • Completion of concrete paving of the eastern roundabout.
  • Start of Frederickton levee and boat ramp construction.

For more information on construction activities click here.

 

Please follow all traffic controller instructions

Slow down in work zones! 

Southern bridge approach at Frederickton Looking north over Boat Harbour Creek arch Looking south towards Southern kempsey interchange
Looking south over Bingus Fauna crossing south of Crescent Head Road Looking south of cut 2 towards Southern Interchange Looking north from cut 2 towards Boat Harbour arch and Rail Crossing Inches Road overbridge girder installation Looking north spray sealing select on approach to Macleay River Floodplain bridge over Frogmore Swamp Placing sub-base concrete at the Frederickton interchange Erecting first girder on Macleay River Floodplain bridge Construction of abutment on Macleay River Floodplain bridge Erecting girders on the Macleay River Floodplain bridge Girders in position on Spans 2 to 8 of Macleay River Floodplain bridge Excavation for first pile cap on river section of Macleay River Floodplain bridge Pile cap formwork mould in place for first pile cap Bridge construction looking north with cranes and pier, headstock and girder erection Bridge construction looking south with five 250 tonne cranes and bridge girders erected Macleay River and Floodplain Bridge construction team and plant Bitumen sealing at the southern end of of the bridge near Old Station Road Construction of Bridge over the Macleay River Surface preparation for bitumen sealing near Old Station Road Work at the northern interchange western roundabout at Fredericton View South from Crescent Head Rd New Crescent Head Rd looking west Backfilling at Boat Harbour Creek View north from Cut 2 towards bridges over railway Reinforced soil wingwall for Boat Harbour Creek arch culvert Installing precast parapets at Frederickton  Interchange View looking west from eastern abutment of Old Station road overpass Select material layer at western Frederickton Interchange Roundabout Boat Harbour Arches Crusher and Screen North Coast Rail BDG Trimming Fill Select pavement Macleay Crossing Construction of long bridge over Frogmore Swamp looking north west towards Frederickton Crane manuvering girder for installation at the northern interchange Earthworks at the northern interchange looking east Earthworks at the northern interchange looking west Frederickton interchange bridge deck construction Girder Installation at the Frederickton Interchange Girders installed over Pattersons Lane Laying turf on the levee embakment along the Macleay River at Frederickton Macleay River Floodplain bridge looking south Preperation for girder installation at the northern interchange overbridge Reinforced earth retaining wall adjacent to North Coast Rail Rockfill activities Sheet piling being installed at Pipers Creek looking north towards Inches Road Inches Road sidestrack work Inches road sidetrack Sheet pile wall at Frederickton Sheet piling at Frederickton for Levee Sheet piling at Frederickton for Levee Temporary rock platform at Frederickton in the Macleay River Temporary rock platform at Frederickton in the Macleay River Temporary rock platform at Frederickton in the Macleay River Temporary rock platform at Frederickton in the Macleay River Steel piles to be used on the bridge over the Macleay River Floodplain piling taking place on the Macleay River Photo taken looking south from Crescent Head Road into Cut 4 as material is being won and screened for construction products Concrete pour for Blade Wall at the North Coast Rail Overbridge House that has been raised as part of the Flood Mitigation works Piling works complete at Frederickton Northern Interchange Commencement of construction of Macleay River and Floodplain Bridge Construction of road embankment and transverse drainage lines at Frederickton Interchang Construction of Reinforced Soil Wall at North Coast Railway Installation of rock fill and preparation for Wick Drain installation on Smithtown Link of Frederickton Interchange Installation of 2 cell 1800mm pipes for major transverse drainage lines at Frederickton Interchange Placement of rock fill foundation layer for approach embankments for Old Station Road Overpass View of Abutment A at Pola Creek looking south along new road formation View of Abutment B at B Pola Creek looking north to Cut 5 Centre Blade pier for south bound bridge over Main Northern Railway line Completed reinforced soil wall for Northern abutment of Bridges over Main Northern Rail line Looking south from Pier 53 at Crane pads for construction of Macleay River and Floodplain Bridge Lifting first pile into position for MRFB Driving of first Pile for MRFB Pile driving in progress at Piers 52 and 53 of MRFB Northern side of the Macleay River, looking south along the new alignment Floodplain on the southern side of South West Rocks Road.  Crane platforms made from recycled tyres filled with rock Floodplain on the southern side of South West Rocks Road.  Crane platforms made from recycled tyres being filled with rock The haul road at Pola Creek which was affected by flooding during the month Looking north from Inches Road Looking south towards Pola Creek View looking north from the southern abutment fill for the Maccleay River and floodplain bridges after the flooding in June Construction of the pedestrian walkway on Crescent Head Road overpass bridge Construction of a reinforced soil wall around abutment piles for the new twin bridges over the main Northern Railway line Water cross at north of Old Station Road Drill and blast preparation at South Kempsey Looking west at the Old Station Road traffic switch Machinery on the bypass Northern interchange roundabout looking south towards Frederickton The northern interchange, looking east towards the Macleay River Sediment base north of Crescent Head Road Kempsey bypass project site office Kempsey bypass project alliance team House raising at South West Rocks Road Crescent Head Road first bridge beam lift Crescent Head Road bridge works Bridge construction over the North Coast railway line Environmental water diversions being used on the project Construction underway on Frederickton levee Access construction at Frederickton
Hauling blasted material Material hauled north across Crescent Head Rd Blast area Cut 3 View of the northern interchange at Frederickton Environmental controls in place at Boat Harbour Creek Works underway on the northern interchange Looking south across Crescent Head Rd Progressive revegetation of cut batters Geotechnical Investigation on test pad Crescent Head Rd Bridge abutment preparation Pipe culvert works Sth Crescent Head Rd Pipe culvert works Sth Crescent Kempsey Bridge Kempsey Bypass construction River Kempsey Township Kempsey bypass site photo Kempsey bypass site photo Kempsey bypass site photo Kempsey bypass site photo