Pacific Highway Upgrade

Devils Pulpit upgrade construction

What happened during August and September 2012

  • Bridge headstock and abutment construction
  • Installation of bridge beams
  • Construction of concrete Bridge deck
  • Construction of retaining walls around Tabbimoble Bridge No. 3
  • Box culvert installation
  • Continuation of bulk earthworks
  • Drainage line construction
  • Foundation treatments
  • Removal of access across Tabbimoble Creek 2 & 3
  • Fencing

Key construction activities during December 2012 to February 2013

  • Sediment and erosion control established and being modified to suit new phase of works
  • Several permanent spill/sediment basins complete, topsoiled and hydromulched Irrigation system for Flood Plain installed and operational
  • Bulk earthworks 90% complete
  • Pavement material under select and sub base being installed in the majority of fills and 1 cut
  • Longitudinal Stormwater pipes being installed
  • Open drains being completed
  • Works on Tabbimoble bridge 2a and 3a approximately 90% complete
  • Trial mixes for concrete sub base and base concrete undertaken batch plant being established on site.