Devils Pulpit upgrade construction
What happened during August and September 2012
- Bridge headstock and abutment construction
- Installation of bridge beams
- Construction of concrete Bridge deck
- Construction of retaining walls around Tabbimoble Bridge No. 3
- Box culvert installation
- Continuation of bulk earthworks
- Drainage line construction
- Foundation treatments
- Removal of access across Tabbimoble Creek 2 & 3
- Fencing
Key construction activities during December 2012 to February 2013
- Sediment and erosion control established and being modified to suit new phase of works
- Several permanent spill/sediment basins complete, topsoiled and hydromulched Irrigation system for Flood Plain installed and operational
- Bulk earthworks 90% complete
- Pavement material under select and sub base being installed in the majority of fills and 1 cut
- Longitudinal Stormwater pipes being installed
- Open drains being completed
- Works on Tabbimoble bridge 2a and 3a approximately 90% complete
- Trial mixes for concrete sub base and base concrete undertaken batch plant being established on site.