"I am writing to thank you for your cooperation in delivering the Australian Government's Nation Building Program …" - Open full testimonial [pdf, 38KB]
The Mulgoa-Jamison Road intersection is in Penrith on the outskirts of Sydney, The area has seen a significant increase in the population size and density over the last two decades and local traffic requirements have subsequently changed.
Roads and Maritime Services (replacing Roads and Traffic Authority) engaged Road & Fleet Services to replace the existing roundabout with a signal-controlled intersection. This enabled pedestrian crossings and additional traffic lanes to be built.
RFS met a number of challenges in this project with utility realignments, community relations, heritage buildings and high-volume vehicle and pedestrian traffic.
Intersection upgrade, Mulgoa–Jamison Roads
Roads and Maritime Services (replacing Roads and Traffic Authority)
$12 million
December 2010
John Kalantzis T 02 8849 2610
Joanna Schultz T 02 9794 4703
The project brief was to:
The project required minimal disruption to pedestrian and vehicle traffic, particularly as a number of local businesses depended on easy access from passing traffic. RFS was also required to construct stormwater drainage, relocate existing utilities and complete the works with asphalt paving and line marking. RFS developed variations on standard work methods to protect some heritage-listed buildings in the area. Those challenges were addressed by RFS in a number of ways.
The intersection carries very heavy traffic in all directions. RFS needed to maintain road capacity and minimise interruption to traffic. This was achieved by staging four separate traffic arrangements – shifting the traffic lanes laterally four times and creating four temporary roundabouts at set stages of the project. Both day and night shifts were operated to minimise traffic disruption.
So as not to disrupt pedestrian movement, temporary footpaths were created between property boundaries and work areas with Paraweb fencing and sign-posting.
The operation to remove the old roundabout, commission the traffic signal controller and replace the line marking was completed in one night. This took considerable planning as well as constant communication with the local community to keep them informed about changing traffic conditions.
It was critical to maintain access to residences and businesses during construction. It was achieved by staging the pavement widening in small sections to ensure ongoing access for local residents. We also provided temporary secure parking while paving went on.
Signs were provided in front of businesses to direct customers into their parking areas. Pavement widening was staged so that there was always access to business premises via side streets.
While the traffic above ground was bad enough, below ground there was congestion of another kind with water and sewerage mains, high-pressure gas pipelines and electricity and telecoms cables all competing for space with the tree roots. We undertook a significant amount of under-boring – to a depth of four metres in places – to get under culverts and avoid the occasional seams of ironstone.
Considerable work went into coordinating utility contractors to prevent one obstructing another.
RFS conducted dilapidation surveys before work started to assess the existing condition of all nearby properties and in particular, a group of heritage houses adjacent to the pavement widening areas. To reduce the risk of vibration damage we used multi-tyred pneumatic rollers (instead of smooth drum) and a sand-cement mix instead of sandstone in the select fill layer.
Asphalt paving at night
The roundabout after the asphalt build up
Installing drainage system
Heritage buildings, brickworkers cottages