The Roads and Traffic Authority in consultation with Kiama Council has investigated options to construct additional access ramps to the Kiama Bypass. Following the display of a shortlist of five options in April and May 2005, further engineering, environment and financial studies have been undertaken to determine the location of the new southbound off and northbound on ramps.
The selected proposal:
The five options put on display were assessed against social, land use, traffic and engineering considerations. Following consideration of the options it was determined that the ramp locations providing the greatest overall benefit for the community were:
Benefits
Greatest reduction of traffic in the Kiama central business district.
Greatest immediate use of ramps.
No height restrictions.
Ramps are most centrally located.
Ramps would cater for future growth.
Most cost effective.
Project Update
The construction works on the north bound on- ramp were commenced in September 2007. The works involve the construction works of the new ramp onto the Princes Highway off Bland Street, construction of a 128m long concrete retaining wall and construction of a new roundabout on Bland Street.
Major works on the south bound off-load ramp were commenced in January 2008. The works involve the relocation of a 160m water main, construction of a new ramp off Princes Highway onto South Kiama Drive and construction works on the new intersection at South Kiama Drive.
All construction works are expected to be completed by late 2008.
Changed traffic conditions
Lane closures are implemented from time to time on Princes Highway as part of the construction works. Motorists are asked to follow all road directions, obey all temporary speed limits and drive with caution through the site whilst work is in progress to ensure the safety of workers and motorists.
Construction hours
Construction hours are Monday to Friday from 7am to 6pm and Saturdays from 8am to 1pm. Some work may be required outside these hours however residents and motorists will be given advanced notification if this is necessary.
For further information
Please contact the project manager on 4221 2434 or email kiama_ramps@rta.nsw.gov.au